Need
help solving a project problem?
Once approved, the project management plan
becomes the basis for implementation, which involves both the
execution process as well as the monitoring and controlling process.
The project plan is the road map for execution. The following are
central precepts of project control:
Work is authorized and performed according to
the approved plan.
Information is collected to determine the
current status of the project.
Variances between the plan and actual status
are identified and analyzed.
Causes for the variances are identified.
If necessary, corrective actions are developed
and assessed.
Recommended corrective actions are reviewed,
approved, and implemented.
Project plans—including baselines—are updated
and communicated.
The
baseline is the most recently approved version of the project
plan. There are baselines for each side of the project triangle:
cost (budget), schedule (time), and scope. When discussed together,
they are often referred to as
project performance baselines. The practice of controlling and
documenting changes to the baseline project plan is referred to as
project change management.
Earned value analysis (also known as variance analysis) is a way to
measure, evaluate, and control project performance. It compares the
amount of work planned with what is actually accomplished to
determine if the project is on track. Earned value analysis uses
various calculations and ratios to measure and report on the status
and effectiveness of project work. Although earned value
calculations are usually done by computer, it is important to know
the basis of each calculation and understand what they mean.
The first step in earned value analysis is to
determine the following three key values:
Planned value
(PV) is the planned cost of work scheduled to be done
in a given time period. The amount of PV is determined by totaling
the cost estimates for the activities scheduled to be completed in
the time period. Planned value is also called the budgeted cost
of work scheduled (BCWS). This information is the base from which we later monitor
progress, discern variances, and initiate corrective actions.
Planned value answers the question “What did we think would happen
by this date and how much did we think it would cost?”
Earned value
(EV) is the planned cost of work actually performed in a
given time period. This is a measure of the dollar value of the work
actually performed. The amount of EV is determined by totaling the
cost estimates for the activities that were actually completed in
the time period. Earned value is also called the budgeted cost of
work performed (BCWP). Earned value answers the question “What really happened
up to this point and how much did we think it was going to cost?”
Actual cost (AC) is the cost incurred to
complete the work that was actually performed in a given time
period. The amount of AC is determined by totaling the expenditures
for the work performed in a given time period. It should include
only the types of costs included in the budget. For example, if
indirect costs were not included in the budget, they should not be
included in AC calculations. Actual cost is also called the actual cost of work performed
(ACWP). Actual cost
answers the question “What really happened up to this point and how
much did it cost?”
Once these values are determined, you can
use them in various combinations to provide measures of whether work
is being accomplished as planned.
Schedule variance
(SV = EV − PV).
Schedule variance is determined by subtracting the planned
value from the earned value. This calculation measures the
difference between the planned and the actual work completed. A
positive result means the project is ahead of schedule; a negative
result means the project is behind schedule.
Cost variance
(CV = EV − AC).
Cost variance is determined by subtracting the actual cost
from the earned value. It measures the difference between the
planned (budgeted) cost and the actual cost of work completed. A
positive result means the project is under budget; a negative result
means the project is over budget.
Once these calculations are made, various
indices or ratios can be used to evaluate the status and
effectiveness of project work. These efficiency indicators provide
valuable information that can be used to control the project. The
two most commonly used indices are the schedule performance index
and the cost performance index.
Schedule performance index
(SPI = EV / PV).
This is a ratio of work performed to work scheduled. The
index is calculated by dividing the earned value by the planned
value. This ratio is a measure of efficiency in the schedule. A
value less than 1 means the project has accomplished less than what
was planned and is behind schedule; a value greater than 1 means the
project is ahead of schedule. Analyzing the SPI several times during
the project provides an indication of how the project is performing
compared to the project plan. This index may also be used to
forecast the project completion date.
Cost performance index
(CPI = EV / AC).
This is a ratio of budgeted costs to actual costs. This index
is calculated by dividing the earned value by the actual cost. This
ratio is a measure of cost efficiency (how efficiently dollars are
being spent). A value less than 1 means the work is costing more
than planned; a value greater than 1 means the work is being
produced for less than planned. For example, a CPI of 0.67 means
that for each $1.00 spent on the project, we produce $0.67 worth of
value. Analyzing the CPI several times during the project provides
an indication of the project’s direction concerning costs.
These indices provide a quick snapshot of the project’s efficiencies at a given point in time. However, they are more valuable when used periodically during the life of the project to track trends and take corrective action. These items can be displayed in reports, spreadsheets, histograms, or graphs.
These indices also provide an element used in
the following calculations to forecast the completion of the
project:
Budget at completion
(BAC) is the
estimated total cost of the project when completed. It is calculated
by totaling the cost of all activities outlined on the work
breakdown structure.
Estimate to complete
(ETC = (BAC − EV) / CPI).
This is the expected additional cost needed to complete
the project. It is calculated by subtracting the earned value (EV)
from the budget at completion (BAC), then dividing the result by the
cost performance index (CPI). This estimate shows the expected
additional cost needed to finish the project, including adjustments
to the BAC based on project performance to date.
Estimate at completion
(EAC = AC + ETC).
This is the expected total cost of the project when
completed. It is calculated by adding the actual cost (AC) and the
estimate to complete (ETC). This estimate includes adjustments to
the BAC based on performance to date.
To learn more about the concepts discussed on this page, see Improving Your Project Management Skills.
Recommended Books
Improving Your Project Management Skills.
American Management Association.
Buy at Amazon