Need
help solving a project problem?
A
risk is an uncertain event or condition that, if it occurs, has
a positive or negative effect on the project objectives (scope,
schedule, or budget). All projects have a certain degree of risk
that needs to be managed. The project manager determines where risks
are likely to affect the project, makes contingency plans for them,
and responds to them when they occur.
The risk management plan, evolving throughout
the planning process, incorporates (1) risk identification; (2)
qualitative and quantitative assessments; (3) strategies for
prevention, detection, and mitigation of loss; and (4) recovery and
restoration of functions.
Projects are investments and the project
manager is responsible for achieving specific benefits within
targets of time, cost, asset utilization, and resource utilization.
However, every investment comes with risks. No one can predict with
certainty the source, timing, significance, or impact of problems.
This chapter describes the risk management
processes of identifying, analyzing, and responding to project risk.
The purpose of risk management is to maximize the results of
positive events and minimize the results of adverse events.
The first step in developing a risk
management plan is to identify the potential risk events.
The following are major categories of
risk:
Technical: new breakthroughs, design errors or
omissions.
Administrative: processes, procedures, changes
in roles or responsibilities.
Environmental: culture of the organization,
change in management or priorities, office politics.
Financial: budget cuts, cash flow problems,
corporate unprofitability, unchecked expenditures, changing economic
conditions.
Resource availability: specialized skills or
critical equipment not available.
Human: human error, poor worker performance,
personality conflicts, communication breakdown.
Logistical: inability to deliver materials or
work face-to-face.
Governmental: legislated regulations.
Market: product fails in the marketplace,
consumer expectations change, new competitor products.
To identify potential risks, simply ask
“What could go wrong?” Review the work breakdown structure for the
project, the cost estimates, and resource plans and consider what
might happen that could cause any aspect of the project to deviate
from the plans. Define specific risk events and describe what
specifically might go wrong. For example, ground breaking may be
delayed because of legal problems in securing the building permit.
Describe the effect of each potential event. Identify what would
cause the risk event to happen (often called triggers) and describe
any conditions or signs that may warn you of the impending event.
Consider both internal and external events that
could affect the project. Internal events are things under the
control of the project team, such as work assignments or cost
estimates. External events are things beyond the influence of the
project team, such as technology shifts or changing economic
conditions.
We typically think of risk as a negative event
that causes harm or loss to the project. However, risk events can
also include opportunities with positive outcomes. A change in
economic conditions may increase the available labor force and allow
you to hire more workers to complete the project sooner. Although a
potentially positive outcome, you need to assess the impact on the
project schedule and cost plans and determine your course of action.
You can never anticipate all possible risks,
nor should you expend the effort to try to identify every
conceivable problem. Simply identify those that are fairly likely.
The cost of prevention should never exceed the cost of impact should
the potential problems actually occur!
Risk identification is not a one-time
event. Economic, organizational, and other factors will change
during the course of the project that may bring to light additional
sources of risk. Risk identification should first be accomplished at
the outset of the project, and then be updated on a regular basis
throughout the life of the project.
Once you have identified the potential
risk events to be included in the plan, the next step is to estimate
the probability of occurrence and determine the impact if the event
were to occur.
You may wish to give greater analysis to
potential risks associated with activities on the critical path,
since a delay in these activities is more likely to delay the final
outcome of the project. Also give attention to points in the network
where activities converge, because these tend to have a greater
degree of risk.
For each potential risk event, estimate its
impact on the time, cost, scope, quality, and resources. Remember
that a single risk event could have multiple effects. For example,
the late delivery of a key component could cause schedule delays,
cost overruns, and a lower-quality product.
To help prioritize the potential risks,
categorize them in two dimensions: likelihood (or probability of
occurring) and the consequences (impacts).
Focus primarily on risks with high impact and a high probability of
occurring. Appearing in the top-right quadrant, these are critical
risks that are more likely to happen and would have a serious
consequence if they do.
In a highway construction project, potential
equipment breakdowns may be one such risk. The impact is great
because construction stops without functioning equipment. You can
influence the probability of such breakdowns by using reliable
equipment and having good preventive maintenance plans.
Next, focus on risks with high impact but low
probability. These appear in the top-left quadrant. In our example
of a highway construction project, such a risk may be the threat of
a union strike over a requested pay raise.
Such a potential risk has great impact because
it would halt construction. But if there is a low probability of the
union calling a strike, you could delegate this potential problem to
company management and union representatives.
Contingency plans should be made for these
types of risks because of their high impact.
Of lesser priority are the risk events that
fall in the bottom two quadrants because their impact on the project
is low. An example of a risk that may appear in the bottom-right
quadrant (low impact but high probability) is late delivery of trees
and bushes for landscaping along the roadside. The impact is low
because traffic may begin using the highway even if the landscaping
is not yet completed. Your contingency plan may be to have an
alternate vendor in place, ready to deliver the trees and bushes if
the primary vendor fails.
Finally, consider the potential risk events in
the bottom-left quadrant (low impact and low probability). An
example of such a risk may be the late arrival of permanent signs
for the highway. The probability of failure on the part of an
experienced vendor may be low. The impact is also low because you
can continue to use the temporary signs until the permanent ones are
installed.
Along with these two factors of impact and
probability, also consider your ability to do something about the
potential risks, either in preventing them from happening or in
responding to their impact when they do happen.
The purpose of risk response is to
minimize the probability and consequences of negative events and
maximize the probability and consequences of positive events.
A response plan should be developed before
the risk event occurs. Then, if the event should occur, you simply
execute the plan already developed. Planning ahead allows you the
time to carefully analyze the various options and determine the best
course of action, so you are not forced to make a quick and perhaps
not well-thought-out response to a threatening situation.
In developing a response plan, consider
ways to avoid the risk, transfer it to someone else, mitigate it, or
simply accept it.
Avoiding.
It may be possible to eliminate the cause, and
therefore, prevent the risk from happening. This may involve an
alternative strategy for completing the project. For example, rather
than assigning work to a new, less expensive contractor, you may
choose to reduce the risk of failure by using a known and trusted
contractor even though the cost may be higher. You can never avoid
all risk, but you can try to eliminate as many causes as possible.
Transferring. It may also be possible to transfer some risk to
a third party, usually for the payment of a risk premium. For
example, you can avoid the chance of a cost overrun on a specific
activity by writing a fixed-price contract. In such a case, the
contractor agrees to complete the job for a predetermined (higher)
price and assumes the potential consequences of risk events. If the
risk is low, you could choose to accept the risk and write a
cost-plus contract, paying the contractor only the actual costs plus
a predetermined profit. Other examples of risk transference include
the purchase of insurance, bonds, guarantees, and warranties.
Mitigating. Mitigation plans are steps taken to lower the
probability of the risk event happening or to reduce the impact
should it occur. For example, you can reduce the likelihood of a
product failure by using proven technology rather than cutting-edge
technology. Mitigation costs should be appropriate to the likelihood
of the risk event and its potential impact on the project. Some
mitigation strategies may not take a lot of effort, but may have
large payoffs in eliminating the potential for disaster. On a
project with a tight deadline, the risk of delayed delivery of raw
materials may be disastrous. If two vendors can provide materials at
essentially the same price, but one has a much larger inventory and
a significantly better history of on-time delivery, choosing the
vendor with the better track record may be an easy mitigation
strategy with a potentially large payoff.
Accepting.
When there is a low likelihood of a risk event, when
the potential impact on the project is low, or when the cost of
mitigation is high, a satisfactory response may be to accept the
risk. For example, midway into a project to reengineer a
manufacturing plant to increase efficiency and output, the economy
moves into a recession. The company chooses to proceed with the
project anyway and accept the risk that lower sales may reduce the
return on investment below what was expected.
After considering the options of avoiding,
transferring, mitigating, or accepting the risk, the outcome of
response planning is a risk management plan, contingency plans, and
reserves. The risk management plan documents the procedures that
will be used to manage risk throughout the project. It lists
potential risk events, the conditions or signs that may warn of the
impending event, and the specific actions to be taken in response.
Contingency plans describe the actions to be taken if a risk event
should occur. Reserves are provisions in the project plan to
mitigate the impact of risk events. These are usually in the form of
contingency reserves (funds to cover unplanned costs), schedule
reserves (extra time to apply to schedule overruns), or management
reserves (funds held by general management to be applied to projects
that overrun).
After identifying your plans to avoid,
transfer, mitigate, or accept the risk, you may need to add specific
activities to the work breakdown structure and other plans.
The project manager and other team members
monitor the project throughout its life, looking for triggers and
signs that may warn of impending risk events. When risk events
happen, corrective action identified in the risk management plan is
taken.
When an unplanned risk event occurs, a response
must be developed and implemented. This is often called a
workaround. After the response is implemented, the risk management
plan should be reviewed and updated if necessary. It may also be
necessary to adjust other project plans or the basic project
objectives.
As changes in the project occur, it may be
necessary to repeat the steps of identifying, assessing, and
planning responses to risk.
To learn more about the concepts discussed on this page, see Improving Your Project Management Skills.
Recommended Books
Improving Your Project Management Skills.
American Management Association.
Buy at Amazon